Actual pack output / invented project

A report you can inspect.

This worked estimate is generated by the same calculation and report modules as the delivered pack. It uses invented prices and a fictional project. Use your browser's Print / PDF command to keep a copy.

Try the free interactive sample · See what is in the pack

YC
Your Construction BusinessYour phone · Your email
EstimateEXAMPLE-0012026-09-06

Garden patio — worked example

Prepared for
Example client (fictional)
Project location
Illustrative site — verify actual measurements

Quantity takeoff

Slab / zoneDimensionsCountVolume (ft³)
Rectangular patio12 × 10 ft × 4 in140
Geometric volume40 ft³Allowance · 10%+ 4 ft³Required volume44 ft³

Each volume = length × width × depth converted to ft × count. Non-overlapping rectangles only. Required volume = geometric volume × (1 + allowance / 100). Displayed quantities are rounded to four decimals; ordering uses full precision.

Selected supply method

Supplier A (example)

2 yd³

Round up the larger of 1.6296 yd³ required or 2 yd³ minimum, to a 0.25 yd³ order increment. 0.3704 yd³ is order surplus beyond the allowed requirement, not a second waste allowance.

Entered-price estimate · USD

Cost itemAmount
Concrete materialUSD 300.00
DeliveryUSD 60.00
Other supplier feesUSD 0.00
Labor · 3 hours × USD 40.00USD 120.00
Other project costs (enter all applicable items)USD 0.00
Direct costUSD 480.00
Contingency · 0% of direct costUSD 0.00
Markup · 0% of cost including contingency (not margin)USD 0.00
Pre-tax subtotalUSD 480.00
Entered tax · 0% · basis: noneUSD 0.00
Estimate totalUSD 480.00

Money is rounded to two decimal places per cost line before totals. Tax is an entered assumption on no amount (tax calculation off). Prices are not live quotes.

Inclusions

Concrete quantity and the cost items explicitly listed. Prices and labor are invented examples, not market quotes.

Exclusions

Excavation, sub-base, reinforcement, formwork, pumping, finishing, curing, permits, inspections and other unlisted work. Enter any applicable costs before using this estimate.

Assumptions and checks

For quantity and cost planning only. Thickness is an input, not a design recommendation. Confirm dimensions, mix specification, access, supplier minimums, yield and local requirements before ordering.

Entered thickness is not a recommendation. Zero prices and zero tax are treated as zero, not as confirmed free supply or a tax exemption. No tax or engineering rules are inferred.